Frank wants to build a new house on his family's property in the country. He has budgeted $34,594 for the entire project. Frank asked two carpenters to each create a bid to build the new house. Each bid identified the cost for each major part of the project using the same house plans with similar quality materials.

5
5.3.A
5.3.K
5
5.3.A
5.3.K
2
3.2.D
5.3.A
5.3.K
2
5.3.K
2
5.3.K
1
3.2.D
Pitanje 1
1.

Estimate (to the nearest hundred) the total of each project bid to determine if Frank has budgeted enough money to select either carpenter.

Handy Dandy Carpenters

+ = + +

Pitanje 3
3.

Can Frank afford both estimate bids?

Pitanje 4
4.

Find the actual amount for each project bid.

Handy Dandy Carpenters

Construction Corral

Pitanje 5
5.

What is the difference between the amount Frank budgeted for the project and the actual cost for Hand Dandy Carpenters?

What is the difference between the amount Frank budgeted for the project and the actual cost for Construction Corral

Pitanje 6
6.

Frank should select